What specific scope
creep issues occurred?
During the initial kick-off meeting to discuss the audit of
the network, the local client stated that they were aware they had not implemented
a number of the required controls for their network and asked to make a change
to the scope in order to help them better understand the mandated federal
security control requirements for their network. In the project charter, the exclusion
statement specifically stated that controls identified as “Not Implemented, but
planned” would be considered as “Not
Satisfied” and would be validated, but
not assessed. The client asked if we asked
if we could take the time to assess the controls to provide the client with
feedback on how to implement the control.
Wanting to assist the client (and
gain favor for future projects), we agreed to this change.
How did you or other
stakeholders deal with those issues at the time?
As noted by Greer (2010), the project team followed some of
the steps for dealing with project scope changes, but not all. Our project team did the following:
1.
Made note of the specific change and discussed
it among the team
2.
Notified the government sponsor of the
change. The sponsor neither agreed nor
disagreed with our decision to provide more assessment; however, they simply said
that they were not doing an assessment of these controls at other sites. We indicated that if we didn’t provide
assessment for controls that were “Not implemented, but planned,” there wouldn’t
be much for us to assess since the site had not implemented the majority of the
required security controls for their network.
Looking back on the
experience now, had you been in the position of managing the project, what
could you have done to better manage these issues and control the scope of the
project?
What we failed to do was the remaining steps recommended by
Greer (2010), which was to update the project scope statement and overall plan
as well as obtain written approval. This was important because this change in
scope ended up adding too much time to a project that already had major time
constraints (it was a six week project that needed three to four months and/or
more personnel to conduct assessments).
We finished the project on-time, but all team members had to work long
hours to get it done.
Greer, M. (2010). The
project management minimalist: Just enough PM to rock your projects! (laureate
custom ed.). Baltimore: Laureate Education, Inc.